Cripple Creek & Victor Gold Mining Company

"Living a Mining Heritage"

Cripple Creek & Victor Video

CC&V has been conducting gold mining and precious metal extraction operations in the Cripple Creek Mining District (District) since 1976.

The District has a rich and colorful mining history.  More than 24 million troy ounces of gold, along with silver, have been recovered from the District since 1890.  Most of the land on which CC&V now operates has been underground mined in the past for its high grade veins. Gold Production, Resources and Reserves

The annual gold production rate from the Cresson Project varies somewhat with about 250,000 troy ounces produced in 2008. 

Startup for the Cresson Project’s gold production was February 1995.  The annual production from 1995 to 2010 is depicted in the following table.

Year

Ore Mined
(tons)

Gold Produced
(troy ounces)

2012 22,735,941 247,987
2011 21,507,403 266,685
2010 22,705,394 233,429
2009 20,557,818 217,609
2008 24,037,481 257,722
2007 22,811,308 281,822
2006 23,459,142 283,486
2005 20,070,829 329,625
2004 20,342,286 329,030
2003 17,104,176 283,866
2002 15,612,175 224,988
2001 11,500,000 214,010
2000 11,300,000 248,000
1999 11,265,000 231,000
1998 10,930,000 230,300
1997 10,087,924 228,164
1996 9,675,819 174,600
1995 8,004,378 76,587